Telenor Telecom
Essay by review • February 20, 2011 • Research Paper • 5,900 Words (24 Pages) • 2,411 Views
Project Management Report of Civil Works,
Installation and Commissioning of Cellular Site (BTS)
Submitted to:
Submitted by:
TABLE OF CONTENTS
TABLE OF CONTENTS 1
Executive Summary 1
Scope of this Document 1
CHAPTER 1 1
HISTORY OF CELLULAR NETWORK 1
1.1 What Is Cellular Network? 1
1.2 A Brief History Of Cellular 1
1.3 Advanced Systems (Cellular Concept) 1
1.4 The Telecommunication Industry In Pakistan 1
1.4.1 Industry Overview 1
1.4.2 Fixed Line Telephony In Pakistan 1
1.4.3 Cellular Telephony In Pakistan 1
1.4.3.1 Existing Players 1
1.4.3.2 Competitive Landscape 1
1.4.4 Growth Trends In Cellular Telephony In Pakistan 1
1.4.4.1 Cellular Telephony Historical Growth 1
1.4.4.2 Historical Market Share Trend Of Existing Cellular Networks In Pakistan 1
1.4.4.3 Requirement Identification Of New Cellular Network In Pakistan 1
1.4.5 Parameters Of Setting Up New Network In Pakistan 1
CHAPTER 2 1
PROJECT CHARTER 1
2.1 Introduction 1
2.1.1 Identifying Main Sources 1
2.1.2 Hardware Requirement 1
2.2 Statement of Work 1
2.3 Project Objectives 1
2.4 Payment Schedule 1
2.5 Project Dependencies & Constraints 1
CHAPTER 3 1
PROJECT MANAGEMENT STRATEGY 1
3.1 General Management Strategy 1
CHAPTER 4 1
SCOPE STATEMENT 1
4.1 Scope / Mission Statement 1
4.2 Responsibilities of the Contractor 1
4.3 Responsibilities of the Contractor 1
4.3 Basic Terms & Condition Of The Turnkey Contract 1
4.3 Limitations in the Scope of Work 1
CHAPTER 5 1
WORK BREAK DOWN STRUCTURE 1
5.1 Work Breakdown Structure 1
CHAPTER 6 1
RESOURCES, COSTING AND SCHEDULE PLAN 1
6.1 Resource Plan 1
6.2 Costing 1
6.3 Schedule Plan 1
CHAPTER 7 1
PERFORMANCE MEASUREMENT BASE LINE 1
7.1 Success Parameters 1
7.2 Technical Performance Measurement Baseline 1
7.3 Project Failure Parameters and Damages 1
CHAPTER 8 1
RISK MANAGEMENT PLAN 1
8.1 Risk Identification and Management 1
8.2 Risk Management Planning 1
8.3 Risk Identification 1
8.4 Qualitative Risk Analysis 1
8.5 Quantitative Risk Analysis 1
8.6 Risk Response 1
8.6.1 Deflecting Of Risk 1
8.6.2 Mitigating Of Risk 1
8.7 Critical Risks 1
CHAPTER 9 1
CHANGE MANAGEMENT PLAN 1
9.1 Change Management (Vendcom) 1
9.2 Change Management (Contractor) 1
CHAPTER 10 1
QUALITY MANAGEMENT PLAN 1
10.1 Quality Policy 1
10.2 Quality Management 1
CHAPTER 11 1
PROCUREMENT MANAGEMENT PLAN 1
Executive Summary
Telenor Cellular Operator is planning to launch its operations in Pakistan on August 14th 2006 as the 1st GM 900 Mobile Operator.
Telenor has signed a multi-million dollars contract with VendCom (an International Telecom Vendor) for the deployment of its GSM Network.
VendCom has outsourced the site preparation / Civil Works and Installation of Telecommunication Equipment to SABRAN Contractors for site on the outskirts of Islamabad and on Highways.
The contract between SABRAN & VendCom will be executed on Turnkey basis i.e. hand over of fully functional Base Station in all respects to integrate with the rest of the network by mid-June.
Scope of this Document
This document covers the planning, deployment and Civil works of only one Base Station site located on the outskirts of Islamabad.
CHAPTER 1
HISTORY OF CELLULAR NETWORK
1.1 What Is Cellular Network?
A cellular network allows cellular subscribers to wander anywhere in the country and remain connected to
...
...